Deviation and forecast

A deviation is plan minus cost, for any filter and date range. Positive is favourable. A forecast is where cost is heading. Both are reports over the same numbers, never records.

Deviation

Deviation of a filter over a date range plan of the filter over the range − cost of the filter over the range

Any filter: a feature, a project, a person, a department, a client. The plan comes from the accepted estimate and, for a person, from their shares. The cost is the one formula.

From the worked month Plan Cost Deviation
Project Shop, March 232.50 800 −567.50, unfavourable
Feature KD-1 500 580 −80, labelled scope
Person Mara, March 139.50 700 −560.50

Each row opens down to the sessions and their summaries. Look at both signs: an unfavourable deviation may be a problem, a favourable one may mean someone can teach the others, or that the next estimate should be lower.

Labels

The System 1 classifier reads the estimate's description and the sessions' summaries and labels why:

Label Meaning
Scope More or less was built than described.
Trouble Agents looped, failed or redid work.
Estimate itself The work was as described and went well; the estimate was off.

Each labelled deviation refits the estimator, so the next estimate for similar work is closer.

Forecast

Forecast of a filter for the next date range computed from the cost of the filter over the past ranges

A forecast is a report: ask for it on any filter, such as the organization, a team or a person, for the next month. Nothing is stored and nothing is sent. An estimate looks at one piece of work; a forecast looks at a filter over time.

No alerts

A deviation sends no alert and stops nothing. Your provider offers spend caps.